Street Repairs Update 8-13-19

The contractor has had more problems getting Asphalt to complete further work on the streets.  With the amount of street work going on in the parish, asphalt suppliers are committed out weeks in advance therefore delaying our project.  The contractor has now gone to another source for his asphalt. He is now 20% complete.

He has restarted the project on Tuesday, August 13, 2019.  His plan is to complete the project in 2-3 weeks.  He will begin work each day around 7:00 AM. He will put out signs each day that work is in progress.